Sidewalk Construction Update
Dear Emerson Community,
The
following ongoing work will occur from Monday, February 10, 2020,
through Friday, February 14, 2020, from 7:00 am – 3:30 pm:
- The focus of the sidewalk work this week will be located inside the enclosure at 80-98 Boylston Street where ongoing demolition and removal of debris will occur through Wednesday.
- Work on the underside of the sidewalk will continue throughout the week.
- No work is scheduled Saturday or Sunday.
Thank you for your continued cooperation.
Peggy Ings
Vice President, Government and Community Relations
617-824-8299
(Visited 31 times, 1 visits today)
Categories