Sidewalk Construction Update
Dear Emerson Community,
The work schedule for the Boylston Street sidewalk project next week consists of the following dates and times:
- Monday, 11/25/19 from 6:00 am to 3:00 pm
- Tuesday 11/26/19 from 7:00 am to 3:00 pm
- Wednesday, 11/27/19 from 7:00 pm to 3:00 am
- Thursday, 11/28/19, holiday, no work
- Friday, 11/29/19 from 7:00 am to 3:00 pm
The work for next week will include:
- Concrete placement
- Removing formwork
- Saw Cutting
- Waterproofing/insulation
- Moving concrete barriers to sidewalk edge
- Removal of steel road plates
- Patch existing excavations at the corner of Tremont and Boylston Street with new asphalt
Thank you for your continued support of this project.
Happy Thanksgiving!
Peggy Ings
Vice President, Government and Community Relations
617-824-8299
(Visited 43 times, 1 visits today)
Categories