The work schedule for the Boylston Street sidewalk project next week consists of the following dates and times: 

  • Monday, 11/25/19 from 6:00 am to 3:00 pm
  • Tuesday 11/26/19 from 7:00 am to 3:00 pm
  • Wednesday, 11/27/19 from 7:00 pm to 3:00 am
  • Thursday, 11/28/19, holiday, no work
  • Friday, 11/29/19 from 7:00 am to 3:00 pm

The work for next week will include:

  • Concrete placement 
  • Removing formwork
  • Saw Cutting
  • Waterproofing/insulation 
  • Moving concrete barriers to sidewalk edge 
  • Removal of steel road plates
  • Patch existing excavations at the corner of Tremont and Boylston Street with new asphalt 