Sidewalk Construction Update
The schedule and the work to be done next week for the Boylston Street sidewalk project is as follows:
- Monday, 12/16/19: Waterproofing and installing concrete caulking at 114 Boylston Street
- Tuesday, 12/17/19: Setting steel bearing plates at 114 Boylston Street and installing an additional temporary ramp
- Wednesday, 12/18/19: (Day Shift) Complete setting of the steel bearing plates at 114 Boylston Street
- Wednesday, 12/18/19: (Night Shift) Complete work at the entryway of Bookstore and ECPD
- Thursday, 12/19/19: (Day Shift) Perform structural steel repair work at 80 Boylston Street entryway
- Thursday, 12/19/19: (Night Shift) Construction barriers to move to allow pedestrians to enter onto new concrete areas
- Friday, 12/20/19: Preparing site at 116 Boylston Street for a concrete pour
Thank you for your continued cooperation throughout this project.
Peggy Ings
Vice President, Government and Community Relations