Sidewalk Construction Update

Dear Emerson Community, 

The schedule and the work to be done next week for the Boylston Street sidewalk project is as follows: 

  • Monday, 12/9/19: No work due to forecast of rain
  • Tuesday, 12/10/19: Concrete pour beginning at 6:00 am until completion
  • Wednesday, 12/11/19: Seal the concrete
  • Thursday, 12/12/19: Waterproof concrete sealant (weather permitting)
  •  Friday, 12/13/19: Reposition barriers to accommodate pedestrians onto new concrete sections

Thank you for your continued support regarding this project.

Peggy Ings
Vice President, Government and Community Relations